(a)You must equip temporary quarters with all safety devices required by API RP 14C, Appendix C (incorporated by reference as specified in § 250.198). The District Manager must approve the safety system/safety devices associated with the temporary quarters prior to installation.
(b)The District Manager may require you to install a temporary firewater system for temporary quarters in production processing areas or other classified areas.
(c)Temporary equipment associated with the production process system, including equipment used for well testing and/or well clean-up, must be approved by the District Manager.
(d)The District Manager must approve temporary generators that would require a change to the electrical one-line diagram in § 250.842(a). \[81 FR 61918, Sept. 7, 2016, as amended at 83 FR 49259, Sept. 28, 2018\]